A salon owner may find the right treatment bed or head spa station months before opening, then discover that the remaining schedule is too short to import it. At that point, buying locally at a higher price may be the only way to keep the opening on track.
If you have a planned opening or refurbishment date, start the furniture discussion early. DONGPIN's usual production period is 35–55 days, depending on order quantity. Sea freight and delivery then add time that varies by destination. For a project with several rooms or customized products, the first conversation should happen while the layout and purchasing budget are still being developed.
The useful question is broader than “How long is shipping?” You need to decide whether the potential benefits of importing directly still make sense after you account for the full landed cost, the opening date and the risk of an unfinished room. This guide helps you compare those choices.
The table below combines DONGPIN's typical production window, the sea freight estimates we use for preliminary planning, and approximately one week for delivery after the goods reach the destination port. It starts after the order and specifications are confirmed; the initial discussion, final configuration, booking, customs clearance and site preparation need their own allowance.
| Destination | Production | Estimated sea freight | Delivery after arrival at local port | Planning total after order confirmation |
|---|---|---|---|---|
| Nearby Southeast Asian markets, such as the Philippines, Vietnam and Malaysia | 35–55 days | 10–15 days | About 7 days | About 52–77 days |
| Australia | 35–55 days | 25–30 days | About 7 days | About 67–92 days |
| Europe and North America | 35–55 days | At least 55 days | About 7 days | At least 97 days; longer for larger orders or slower routes |
These are planning estimates, not promised delivery dates. The final schedule depends on the confirmed products and quantity, vessel availability, the exact ports, customs processing and the delivery address. A carrier's ocean transit estimate is also different from the complete door-to-door journey: documentation, loading, unloading and customs add steps on both sides of the voyage. Maersk explains this distinction in its ocean freight guidance. The table is only arithmetic; it leaves no extra allowance for booking changes, import formalities, installation or testing.
Before production can be scheduled, the furniture selection has to match the business. A buyer might initially ask for one electric beauty chair, then realize the same project also needs head spa beds, technician stools, nail stations, reception furniture and coordinated finishes. Room dimensions, electrical specifications and plumbing locations can affect the final product choice.
An early conversation with DONGPIN gives the project team time to confirm:
which services each room will offer and how many stations are needed;
the models, quantities, upholstery colors and any requested customization;
access around beds and chairs, plus power, water and drainage requirements;
the destination, expected opening date and local delivery address;
who will manage freight, import clearance and installation at the destination.
The more complete the requirements are, the easier it is to confirm a realistic production and shipping plan. For a full salon project, share a floor plan or room measurements when available. You do not need every finish decided before making contact, but you should avoid waiting until the opening date is fixed and the construction work is nearly complete.

When you are furnishing several rooms, you can choose head spa beds, treatment beds, chairs and supporting furniture as one project. Comparing dimensions and finishes together helps you plan a consistent salon and reduces the chance of choosing a last-minute substitute that does not fit the room. It also gives you time to check practical details: clearance around a bed, plumbing for a wash basin, and the working space around a nail station.
Direct contact early in the project gives you time to ask about model choices, colors, quantities and possible customization. This can be valuable for a salon with a defined design concept or a distributor planning a repeatable product range. The tradeoff is that specifications must be agreed clearly before production. A change after confirmation can affect cost or timing. Ask which options are actually available for the models you choose.
Some buyers contact DONGPIN after finding that the local price for their preferred product is higher. A planned direct order gives you an option to compare. But the product quotation is not the full cost of importing. Direct supply is attractive when its landed cost and schedule both work for your project; it is not automatically the cheapest choice for every quantity or destination.
An earlier commitment. Production and sea freight are real calendar commitments. You may need to confirm models, finishes and quantities while other fit-out decisions are still under way. If the renovation is almost complete, an overseas order may arrive too late for the planned opening.
A complete cost comparison. Build an estimate for the furniture ready for use, rather than comparing a factory product price with a local installed price:
Product price + international freight and any insurance + destination duties and taxes + port and clearance charges + local delivery + installation = estimated landed and installed cost.
Who arranges and pays for each step depends on the agreed trade term and sales contract. The International Chamber of Commerce's Incoterms guidance explains how trade terms allocate delivery tasks, costs and risks. Ask for the named place and delivery term on the quote, and ask a local freight or customs partner to check destination charges.
More coordination across the journey. A vessel schedule can change, customs may request more documentation, or a site may not be ready when goods arrive. Discuss packaging, damage reporting, replacement parts and installation support before ordering. For powered furniture, confirm voltage, plug type and any local documentation or compliance needs for the destination. These are practical planning tasks, not reasons to rule out importing.
Local stock can be the sensible choice when an essential chair or bed is needed in weeks, when you need to inspect an individual unit before purchase, or when a local supplier includes installation and service you value. If a treatment room cannot open without one item, avoiding downtime may be worth more than the price saving on that item.
The tradeoffs are price and choice. In situations DONGPIN has seen, buyers who ran out of time had to purchase a suitable product locally at a higher price. The premium varies by market and supplier; a local quote may also include services excluded from an import quote. Locally available finishes or models may differ from the original design. Compare the same product scope, delivery point and after-sales support.
| Situation | Direct DONGPIN order may fit better | Local purchase may fit better |
|---|---|---|
| Several rooms with a known opening date months away | Time to plan a coordinated furniture package | Useful for one urgent missing item |
| An essential station needed within a few weeks | Production and sea freight may miss the date | Existing stock can keep the room operational |
| Distributor planning repeat purchases | Reorders can follow a stock forecast | Local inventory can cover unexpected demand |
| Buyer values immediate inspection and installation | Plan samples, specifications and support early | Often easier to inspect and arrange service nearby |
A mixed approach can also work: buy one urgent item locally, then import the remaining planned furniture or later replenishment. Keep model and finish choices aligned so the short-term purchase does not create a mismatch. The right answer depends on the value of opening on time and the full cost of each route.
Importing furniture can offer a wider choice of models, finishes and configurations. It also requires time. If the order is placed too late, the buyer may have to choose from locally available stock, accept a substitute that does not fit the original design, or pay more to meet the deadline.
Consider a head spa opening in a nearby Southeast Asian market. Even on the shorter shipping route in our planning table, 35 days of production + 10 days at sea + about 7 days for local delivery = approximately 52 days after order confirmation. That is before any time spent agreeing on the specification or handling a delay. A customer who begins purchasing only a few weeks before opening has little room to recover.
For Europe or North America, the same calculation starts at 35 + 55 + 7 = at least 97 days. A larger order requiring 55 days in production would bring that baseline to at least 117 days. The project still needs time for pre-order decisions, port handling, customs and installation. This is why an attractive product price alone cannot determine when to place the order.
There are two possible costs of delay: paying more for an available local substitute, or leaving a finished room idle while furniture is still in transit. The latter can postpone appointments while rent, staffing or marketing commitments continue. Use your own forecast to compare the options: estimate the appointments lost during a delay, the contribution margin per service and fixed costs that cannot move. If that project impact exceeds the savings from importing, a local purchase for the urgent item may be the more economical decision. The cheapest unit price is not always the cheapest project outcome.

Work backward from the date when the furniture must be on site and ready for installation, rather than from the public opening date. Use the following starting points for an initial conversation, then adjust them with DONGPIN and your freight partner for the actual order:
| Project destination | When to begin discussions before the required on-site date |
|---|---|
| Nearby Southeast Asian markets | Around 3–4 months ahead |
| Australia | Around 4–5 months ahead |
| Europe or North America | Around 5–6 months ahead, or earlier for a large or customized project |
These windows intentionally include time beyond the arithmetic production and transit totals. They give you room to select products, confirm specifications and respond to changes in the shipping schedule. If the project includes several service areas, coordinate the complete furniture list early so that one late item does not delay the opening of a room.
Once the models and quantities are confirmed, ask for a project-specific production estimate and a current freight quotation. Record the planned completion date, shipping route, arrival port, local delivery arrangement and installation date in the same schedule. Recheck those milestones as the project progresses.
For distributors, the same backward plan can become a replenishment cycle. Track how quickly each model sells, decide how much stock to hold, and order again before existing stock reaches that level. A forecasted reorder is easier to manage than replacing a sold-out item after a customer has set an opening date.
Confirm the room plan. Share a floor plan, door and lift access, service areas and station count. Check the footprint and connections of the chosen products.
Confirm the exact furniture list. Record models, quantities, finishes, upholstery, accessories and power requirements. Ask which choices affect production time.
Confirm what the quote includes. Record the delivery term, named place, packaging scope and who handles freight, insurance, clearance, local delivery and installation.
Use one milestone schedule. Put order confirmation, production completion, shipment, port arrival, local delivery, installation and opening on the same calendar. Leave a buffer between installation and opening.
Compare complete options. If time is tight, request a local delivered-and-installed quote for the urgent item and a landed-cost estimate for the planned import. Make the decision using total cost and the value of opening on time.
The best time to contact DONGPIN is when you know the services you intend to offer and have an approximate opening schedule, even if the salon design is still evolving. Our team can discuss individual beauty chairs, treatment beds, head spa and shampoo furniture, manicure stations and a coordinated furniture package for the wider salon.
Share your destination, target on-site date, floor plan if available, preferred products and estimated quantities. We can then help you narrow the selection and build a purchasing schedule around the project. Ask your shipping and import partners to verify the route and destination costs. Early planning gives you more choice and reduces the risk of paying a premium for a rushed local substitute.
Explore DONGPIN beauty salon furniture and contact our team to discuss your next project.
Production generally takes 35–55 days, depending on the order quantity and the confirmed product requirements. Ask for an order-specific estimate before fixing your opening schedule.
For preliminary planning, allow about 10–15 days to nearby markets such as the Philippines, Vietnam and Malaysia; 25–30 days to Australia; and at least 55 days to Europe or North America. The exact route and current vessel schedule can change the estimate.
No. In DONGPIN's preliminary planning, allow about one additional week after arrival at the destination port for local delivery. Customs processing, port handling and installation may require more time and should be confirmed for your shipment.
Contact us while you are planning the layout and budget. As a starting point, begin discussions 3–4 months before you need furniture on site for a nearby Southeast Asian project, 4–5 months for Australia, and 5–6 months or earlier for Europe or North America. Confirm the final timeline against your order and shipping route.
No. Compare the full landed-and-installed import cost with the local delivered-and-installed price. If an essential room would otherwise open late, a higher local price may be justified by the cost of delay.
Check whether a suitable urgent item is available locally. You can still plan a direct DONGPIN order for other rooms or later replenishment, subject to the confirmed timeline and budget.